Description of the steps
Contact ANME
Select a pair of auditors, draft a contract and send it to ANME for approval.
Sign the approved contract and return it to ANME.
To have the AEP report validated – “Functional Program and Preliminary Design” phase.
Have the Preliminary Design (APD) phase of the Water Supply Planning (AEP) report validated.
Obtain a building permit and provide ANME with a copy of the energy performance study.
Have the Final Studies and Tender Document Preparation phase of the Water Supply Planning (AEP) report validated.
Partial payment of the audit team.
Sign a program contract with ANME
Select a construction service provider and carry out the work.
Validate the AEP report – ‘Work Completion and Acceptance’ phase
Final payment to the audit team
Submit a written request for the release of bonuses